Views: 0 Author: Site Editor Publish Time: 2022-07-01 Origin: Site
1. The boiler body is installed, the furnace wall and insulation work are completed, and the natural maintenance is 5-7 days;
2. The trial operation of each boiler system has been completed;
3. The thermal instruments and measuring points required for the oven have been installed and calibrated;
4. Prepare enough fuel for the oven (such as firewood, bottom material, carbon block);
5. Contact the turbine personnel to fill the boiler with water to ensure that the water level is at the normal water level.
6. After inspection by the testing department, the hydraulic test is qualified.